No closure notice has been posted for Livorna Park at 2615 Miranda Avenue. Contra Costa County's construction bids for the park are due Wednesday, October 14, at 2:00 p.m. The county's schedule puts the start of work in fall 2026 and the reopening in December 2027.
The timing creates a problem the county's project pages don't mention. The closure is expected to start in fall, when the closest replacements are cutting back too. Hap Magee Ranch Park's water feature shut for winter on October 1, and its dog park has had a winter moratorium in past years. The weeks before construction starts are the last stretch when Livorna works the way it always has.
The county's July 7, 2026 Public Works presentation said the work was "scheduled to begin the fall of 2026." That's a forecast. As of today, the county's online planroom still shows the Livorna Park Improvements Project as "Accepting Bids." No public sources so far show a contract award, a closure date or a fencing notice.
The published dates so far:
You'll see two different cost figures. The July presentation estimated construction at $3.75 million to $4 million. The bid notice puts the base-bid construction contract at $2,520,000, and that base bid is what the contract is awarded on. The two numbers measure different things, so the gap doesn't mean the budget was cut. The project is still on the same course. The bid results will show what contractors think the work costs.
The county's March 2025 renovation masterplan described what's there now. The playground is worn out. The sports court is striped for half-court basketball and full-court tennis, but the tennis net is gone. The park also has bocce courts and a pavilion, and it hosts summer concerts and movies, family events and everyday visits.
The Notice to Contractors lists the work to be built. Here's how it compares with what's there now:
| Feature | In the 2025 masterplan's description of today's park | In the September 2026 bid scope |
|---|---|---|
| Playground | Aging, described as deteriorating | Playground upgrade |
| Basketball | Half-court striping on shared court | Basketball court |
| Tennis | Full-court striping, net missing | Not listed |
| Bocce | Existing courts | Bocce court |
| Water play | None described | Mist play area |
| Shade | Pavilion | Shade structures |
| Restrooms | Existing restroom building with fixtures that don't meet current ADA requirements | Bathrooms |
| Seating and paths | Walking paths and deteriorated benches | Benches, walkways, paving, bike racks, drinking fountain |
The bid also covers site work: retaining walls, lighting, landscaping, irrigation and utilities. The masterplan found that the restroom fixtures don't meet current ADA requirements and that the benches had deteriorated, and it recorded community requests for more shaded benches and tables.
The "cooling features" from the July presentation turn out to be a mist play area. That makes sense for a park whose biggest crowds come on summer concert evenings. The July presentation also promised tree preservation and native plantings, which fits the landscaping and irrigation lines in the bid.
Pickleball players should check the details. The county's earlier Livorna Park FAQ said the court is striped for pickleball and floated adding another pickleball court. The bid summary names basketball and bocce and doesn't mention pickleball or tennis. The full drawing set, a 142 MB file, is available only to registered planroom users. The final court layout should stay an open question until the county publishes more.
The closest replacement for Livorna's playground and picnic space is Hap Magee Ranch Park on the Danville side. The Town of Danville lists a children's water feature, a covered picnic area, a dog park, restrooms and walking trails, plus a Picnic Area Use Application for groups. The Town also lists separate play areas for younger and older children. That covers a lot of what Livorna's playground does now.
The seasonal rules work against anyone planning to rely on it this fall. The water feature runs April 1 through September 30 and closed for winter on October 1. Danville posted a dog park winter moratorium alert on December 1, 2025, and a later dog-park alert carries an April 23, 2026 date. If the Town follows a similar schedule this year, the off-leash area could close around the same time Livorna closes. Check the Town's alerts page for this year's dates before you plan around it.
The Iron Horse Regional Trail stays open year-round. The East Bay Regional Park District lists staging areas at Danville Boulevard, Lisa Lane and Stone Valley Road. The trail is open 5 a.m. to 10 p.m. unless posted otherwise, and dogs are allowed. It runs through downtown Alamo and past Alamo Square on its way into Danville. North of Alamo, the trail's Robert I. Schroder Pedestrian Bridge over Treat Boulevard is closed for county repairs from October 5 through December 31, 2026. Crews work overnight, 9 p.m. to 5 a.m., Sunday through Thursday. That only matters on rides headed toward the Pleasant Hill area.
For a bigger outing, Las Trampas Wilderness Regional Preserve is at 18012 Bollinger Canyon Road. It has 6,050 acres of hiking and horseback-riding trails, plus two first-come, first-served picnic areas, Steelhead and Shady, near the main parking lot. The park district says to carry your own water. A Women in Wilderness Las Trampas Peak Hike is on the calendar for Saturday, October 24, 2026, at 9 a.m. None of these places replaces a short walk to a neighborhood playground, and that's the gap the closure leaves.
Losing the concert series hits the community calendar hardest. In March 2026, the Board of Supervisors approved up to $48,300 from County Service Area R-7 for the 2026 Summer Concert Series at Livorna Park. For 2027, the county's July presentation says only that construction "will interrupt" the series. No public sources so far name a temporary venue, whether Hap Magee, Alamo Plaza or somewhere else. Watch the next Board agenda that allocates CSA R-7 concert money, because that's where a 2027 location would first show up.
The next county project in central Alamo is also a 2027 item. Crosswalk improvements at Danville Boulevard and South Avenue, estimated at $453,000, are in design and expected to be built in 2027.
With the park expected to close, the next few months of Alamo events happen indoors or at the plaza.
The bids opened in Martinez on October 14 will set the rest of the timeline. The award and the start of construction decide when the park closes. If the county keeps to its schedule, Livorna reopens in December 2027 with renovated bathrooms, shade structures, a mist play area and a new playground.
At Serean Kimmel, we follow county projects like Livorna Park because they change how Alamo homeowners spend their days, and they come up when buyers ask what's happening on a street. If you live near Miranda Avenue and want to talk through how the renovation timeline fits your plans, reach out for a conversation or a free home valuation.
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.